Liza Destiny FPSO Arrives in Guyana

October 2019

Following its voyage west from Singapore and around the African continent, the Liza Destiny arrived in Guyana on August 29. The FPSO cleared customs, and the installation of all 16 mooring lines was completed on September 12. The FPSO’s godmother, Sandra Granger, the First Lady of the Co-operative Republic of Guyana, toured her godchild after its early arrival at the Stabroek Block.

 

With the vessel safely moored on location, workers have been working diligently on the topsides commissioning activities. Along with the gas turbine generators (GTGs), main and injection gas compressors and water injection pumps, the sea water lift pumps were also commissioned. The sea water lift pumps provide the cooling water, utility water, water injection and water for firefighting applications for the FPSO. These pumps could only be commissioned once the vessel arrived in Guyana.

Workers are also working to connect the subsea umbilicals, risers and flowlines (SURF) to the FPSO. The umbilical and riser hook-up commissioning work began in early October and is ongoing. This will be the last major commissioning activity before the project goes onstream.

Related Articles

January 2020

The Liza Phase 1 project achieved first oil on December 20, 2019! The Liza Phase 1 project made history...

January 2020

During 4Q the Saipem Constellation vessel, referred to as SCON, completed the final riser recovery and hookups to the...

January 2020

During October, the Saipem Constellation vessel completed the installation and hookup of the main static and dynamic umbilicals for...

January 2020

Three key workshops were held during the last two quarters of 2019: the Operations Readiness Review (ORR), the SBM...