Liza Phase 1 Timeline

The project leadership team collaborated in 2016 and then expanded to include EPC contractors to establish these strategic milestones in 2017 to guide the project performance and drive accountability to the various leaders and organizations.

2017
completed
Commence FPSO FEED Work
completed
Issue Near / Long Term Logistics Services ITTs
completed
Award FPSO Critical Equipment Packages
completed
Award EPC2 Subsea Systems Contract
completed
Obtain EIA Approval
completed
Award SURF EPC3 Tie-Back System Contract & Umbilical PO
completed
Obtain Production License Approval
completed
Final Investment Decision
completed
Authorize FPSO EPCI, Charter and O&M Work
completed
Execute Line Pipe PO
completed
Provide Final Vessel Motions
completed
Final Tree System Design Review Complete
completed
Finalize Riser Layout at Lower Riser Balcony
completed
Establish All Interface Agreements
completed
Execute PO for Riser / Umbilical Pull-in System
completed
Start FPSO Vessel Conversion
completed
Agree Preliminary Installation Plans & Schedule
2018
completed
Start FPSO Topsides Module Fabrication
completed
Complete High Res Baseline Seismic Survey Acquisition
completed
Near Term Logistics Services Operational
completed
FPSO Financial Close
completed
Commence Production Manifold Fabrication
completed
Spud First Development Well
completed
Deliver FLET/PLET/ITA hubs, valves, caps and 1” flooding caps to EPC3
completed
Deliver Final FPSO Critical Path Equipment Package
completed
Deliver FLET/PLET/ITA 2” flooding caps to EPC3
completed
Last Delivery of Company Provided SURF Items to FPSO Shipyard
completed
Weld Procedure and AUT Qualifications Complete
completed
Saipem Guyana Shorebase ready to Receive Pipe
completed
Long-Term Logistics Services Operational
completed
First 2 Tree Systems Available for Development Drilling
completed
Asphaltene Inhibitor Selection
completed
Liza Production Organization Established
completed
Lift Final Topsides Module on to FPSO
2019
completed
SURF Critical Equipment / Materials Ready for Loud-Out
completed
Mobilize SURF Installation Spread
completed
FPSO Mooring System Pre-installed
completed
All First Oil Trees Delivered
completed
FPSO Sail-Away
completed
Complete Installation of Company-provided Equipment
completed
Initiate Riser Pull-In
completed
7th First Oil Well Complete
completed
Project Onstream
2020
All Facilities Operational and Production at Capacity