Liza Phase 1 Timeline
The project leadership team collaborated in 2016 and then expanded to include EPC contractors to establish these strategic milestones in 2017 to guide the project performance and drive accountability to the various leaders and organizations.
2017
Commence FPSO FEED Work
Issue Near / Long Term Logistics Services ITTs
Award FPSO Critical Equipment Packages
Award EPC2 Subsea Systems Contract
Obtain EIA Approval
Award SURF EPC3 Tie-Back System Contract & Umbilical PO
Obtain Production License Approval
Final Investment Decision
Authorize FPSO EPCI, Charter and O&M Work
Execute Line Pipe PO
Provide Final Vessel Motions
Final Tree System Design Review Complete
Finalize Riser Layout at Lower Riser Balcony
Establish All Interface Agreements
Execute PO for Riser / Umbilical Pull-in System
Start FPSO Vessel Conversion
Agree Preliminary Installation Plans & Schedule
2018
Start FPSO Topsides Module Fabrication
Complete High Res Baseline Seismic Survey Acquisition
Near Term Logistics Services Operational
FPSO Financial Close
Commence Production Manifold Fabrication
Spud First Development Well
Deliver FLET/PLET/ITA hubs, valves, caps and 1” flooding caps to EPC3
Deliver Final FPSO Critical Path Equipment Package
Deliver FLET/PLET/ITA 2” flooding caps to EPC3
Last Delivery of Company Provided SURF Items to FPSO Shipyard
Weld Procedure and AUT Qualifications Complete
Saipem Guyana Shorebase ready to Receive Pipe
Long-Term Logistics Services Operational
First 2 Tree Systems Available for Development Drilling
Asphaltene Inhibitor Selection
Liza Production Organization Established
Lift Final Topsides Module on to FPSO
2019
SURF Critical Equipment / Materials Ready for Loud-Out
Mobilize SURF Installation Spread
FPSO Mooring System Pre-installed
All First Oil Trees Delivered
FPSO Sail-Away
Complete Installation of Company-provided Equipment
Initiate Riser Pull-In
7th First Oil Well Complete
Project Onstream
2020
All Facilities Operational and Production at Capacity