Liza Phase 2 Timeline

2018
completed
Sign/Execute FPSO FEED1-EPC1, Charter and O&M contracts
completed
Award SURF EPC2 (Subsea Systems) Contract with Umbilical and UMCS
completed
Award SURF EPC3 (Tie-Back System) Contract
completed
Execute Line Pipe Purchase Order (PO)
completed
Award FPSO Critical Long Lead Equipment Packages
completed
Establish Key Interface Agreements and Process
2019
completed
Start Production Manifold Fabrication
completed
Agree Preliminary Installation Plans and Schedule
completed
Obtain Development Plan Amendment Approval
completed
Environmental Permit Receipt
completed
Final Investment Decision
completed
Execute PO for Riser Pull-in System and Umbilical Pull-in System
completed
Commence Linepipe Coating
completed
MPF Hull Launch from Dry Dock at SWS
completed
Start FPSO Topsides Module Fabrication
completed
Deliver Production FLET/ITA Hubs & Valves to EPC3
completed
Deliver Production FLET/ITA Caps to EPC3
Commence WAG Manifold Piping Assembly
completed
Deliver Flexjoint Receptacles / Mock-ups to Integration Yard
completed
Deliver Umbilical I-tube Extension to Integration Yard
First Two Tree Systems Available for Development Drilling
2020
Spud First Development Well
Start MPF Dry Dock at Integration Yard
Deliver Final FPSO Critical Path Equipment Package
Mobilize SURF Installation Spread (FDS2) – Campaign 1
Deliver Subsea Controls Equipment to Integration Yard
All Production & WAG Foundations/Piles Ready for Loadout
Commence 4D Seismic Survey
Lift Final Topsides Module onto FPSO
FPSO Piles and Mooring Lines Pre-Installed at Production Location Offshore Guyana
Complete Flowline & Riser Offshore Installation – Campaign 1
Flexjoint Ready for Loadout
Umbilicals Ready for Loadout at UK
2021
FPSO Sail-Away from Integration Yard
SURF Campaign 2 Critical Equipment / Materials Ready for Load-out
Fiber Optic Cable Installation Complete
Commence Jumper Final Assembly
Mobilize Main Installation Vessel – Campaign 2
Complete FPSO Mooring
Initiate Riser and Umbilical Pull-ins
Complete FPSO/Facilities Commissioning Required for First Oil
Complete Installation of Well Jumpers (available), all Flowline Jumpers, and Distribution System
2022
Project Onstream
First Lift
All Facilities Operational and Production at Capacity