Drilling
The Guyana Drill team is celebrating success after landing four wells in the reservoir zone during development drilling operations.
The liquid mud plant is also now operational in Georgetown. The drilling mud is critical for circulation by keeping the wellbore clear of drill cuttings.
To understand the scale and size of the operation, visit the ExxonMobil Guyana Facebook page for a video tour of the Noble Bob Douglas drilling rig when it arrived in Guyana.
Logistics
Logistics assets and infrastructure are operational to support offshore installation activities, continued development drilling and initiation of production operations.
Achieving this to schedule involved excellent planning and contractors who met their commitments to deliver the assets and get the shorebase ready.
Guyana Shorebase with two Platform Supply Vessels docked quayside for night loading
Liquid Mud Plant operational in Georgetown, Guyana
Noble Bob Douglas
Related Articles
January 2020
The Liza Phase 1 project achieved first oil on December 20, 2019! The Liza Phase 1 project made history...
January 2020
During 4Q the Saipem Constellation vessel, referred to as SCON, completed the final riser recovery and hookups to the...
January 2020
During October, the Saipem Constellation vessel completed the installation and hookup of the main static and dynamic umbilicals for...
January 2020
Three key workshops were held during the last two quarters of 2019: the Operations Readiness Review (ORR), the SBM...