Fabrication and construction activities continue to progress well for the Liza Unity FPSO.
The accommodation block was recently lifted onto the Multi-Purpose Floater (MPF) hull and the MPF launched from dry dock on June 8 at the Shanghai Waigaoqiao Shipbuilding Co. (SWS) shipyard. It is now moored quayside for additional construction work, mechanical completion and commissioning.
Activities are on track for the MPF to depart for the Singapore integration yard by the end of this year. Get a high level view of the MPF leaving dry dock in this video.
Topsides module fabrication has begun at Dyna-Mac in Singapore, with the strike steel ceremony taking place on May 24.
Bulk procurement and main equipment deliveries are progressing as planned. Looking ahead to the third quarter of 2019, the mooring structure pre-fabrication is slated to begin at Keppel Shipyard in Singapore, system commissioning work for the MPF will start at SWS, and the 3D model of the FPSO will undergo its 90 percent review at SBM Offshore in Kuala Lumpur, Malaysia.
Related Articles
January 2020
The Liza Phase 2 FPSO team achieved a key milestone during the fourth quarter with receipt of the MPF’s...
January 2020
The team achieved an important strategic milestone during 4Q19 as OSI completed the manufacturing, testing, and delivery of all...
January 2020
The Liza Phase 2 Subsea team achieved a number of key milestones during the fourth quarter. One milestone was...
January 2020
During the fourth quarter, the Guyana Wells team welcomed a 4th rig to the project, the Noble Don Taylor....