Liza 1

January 2019

January 2019

A three-day Contractors Safety Management Workshop themed “Building a Strong Safety Culture” was held in Georgetown in November. The...

January 2019

During the fourth quarter of 2018, SBM and Keppel safely completed the second dry dock for the Liza Destiny...

January 2019

The shorebase in Trinidad has been busy receiving and testing subsea equipment over the last four months. TechnipFMC (TFMC)...

January 2019

Riser and flowline pipe coating has been completed at Shawcor’s Channelview and Veracruz facilities. A significant milestone for Liza...

January 2019

The Liza Phase 1 Subsurface team has been focused on landing eight wells into the reservoir by the end...

January 2019

As we work toward first oil, ExxonMobil and SBM have invested significant time and effort in building the organization...

November 2018

November 2018

This is being shared worldwide across the company and is being cascaded to our EPCs and subcontractors. It is...

November 2018

Liza Destiny: Plans are on target. From getting the FPSO vessel into drydock to fabrication of the suction pile...

November 2018

The first and second of 17 tree systems engineered and manufactured by TechnipFMC are bound for Trinidad. This follows...

November 2018

Due to its ability to deliver complex projects safely and efficiently for deepwater field developments, the Saipem Constellation, a...

November 2018

The Guyana Drill team is celebrating success after landing four wells in the reservoir zone during development drilling operations....

July 2018

July 2018

Our commitment to Security, Safety, Health and the Environment (SSHE) is the foundation of the Liza Phase 1 project.